An ACR doesn’t expire on a set date. It describes one version of your product on one date, so update it when the product changes in ways that affect accessibility, such as a major release or a redesign, and when a buyer asks for a newer report, WCAG version or template. Checked on .
Key Takeaway
The date and version on the first page are what a reviewer checks. A report on a version you no longer sell, or with no version at all, gets questions no matter how good the testing was. Keep the version current, note every revision, and re-test what changed before you change an answer.
Does an ACR Expire?
No. ITI, which publishes the VPAT, sets no expiry date, and its VPAT page says nothing about how long a finished report stays valid. Section508.gov doesn’t set one either. What it does say, in its ACR FAQ, is that every time a product is changed or updated, such as a version change or a bug fix, an updated ACR may be required to address any changes in the product’s accessibility.
A report covers the version named on its first page, as it was on the report date. ITI’s template asks for the product version and a report date with at least the month and year, so a reader can always tell what was tested and when. Once you ship a version the report doesn’t describe, the report hasn’t expired, but it’s describing a product the buyer can’t buy.
What Should Trigger an Update
- A release that changes the interface. New screens, new flows, a new navigation pattern or a rebuilt component library. Section508.gov’s change-control guidance tells agencies to make sure vendor patches, releases and enhancements come with updated ACRs and accessibility regression testing results.
- A redesign. The same guidance calls for accessibility checks after any significant user interface or user experience change. A new design system can change every row in the report at once.
- A new module, or a product swap in a contract. Section508.gov’s model contract language asks for an ACR for each ICT item that is developed, updated or configured for the agency, and when product substitutions are offered.
- A fix that changes an answer. If your team fixed the problem behind a Partially Supports row, a re-test and a revised report let you show it. The reverse matters too: a regression that breaks a row marked Supports makes the report wrong.
- A buyer asks for a newer WCAG version. A report tested against WCAG 2.1 doesn’t answer a 2.2 requirement. More on that below.
- A buyer asks for the current template. ITI’s current version is VPAT 2.5Rev, dated April 2025. Section508.gov says any VPAT 2.x is acceptable, while its model contract language says the ACR should be based on the latest VPAT version, so read the solicitation. A report built on the Original Section 508 Standards from 2001 has to be redone against the Revised Standards from 2017, and section508.gov says so outright.
- A buyer asks for a report less than a set age. Some do, in writing. See the next section.
How Old Can an ACR Be for an RFP?
It depends on the buyer, and the solicitation decides. We haven’t found an official federal number for how old an ACR can be. Section508.gov’s guidance points at the version instead. It tells agencies to test final, commercially available release versions, and its model contract language asks for an ACR for each item based on the latest VPAT version. A report on last year’s release can fail that test whatever its date says.
Some questionnaires do set a window. The HECVAT that colleges and universities send vendors asks, in its ITAC‑06 question, whether a VPAT or ACR has been created or updated for the solution and version under consideration within the past 12 months, and it’s one of the questions the workbook marks critical. That’s from version 4.1.6, read on September 14, 2026, and how to answer the accessibility questions in a HECVAT covers every row. Outside a document like that, the honest answer is that it varies. If an RFP names a window, that window is the rule. If it doesn’t, a report on the version you’re selling, with a recent date and revisions explained, is the safest thing to send.
| Source | What It Says | What It Means for You |
|---|---|---|
| Section508.gov, ACR/VPAT FAQsection508.gov/sell/acr-vpat-faq | Every time a product is changed or updated (for example a version change or bug fix), an updated ACR may be required to address any changes in its accessibility. A report built on the 2001 Original Section 508 Standards must be updated to the 2017 Revised Standards. | The report follows the product. There is no expiry date, but there is no free pass for old versions. |
| Section508.gov, Change Controlsection508.gov/manage/governance/section-508-for-change-control-processes | Agencies should make sure vendor patches, releases and enhancements come with updated ACRs and accessibility regression testing results, and should check accessibility after significant UI or UX changes and, for high-impact systems, on a recurring cadence such as quarterly. | A federal customer can ask for an updated report with each release you deliver to them. |
| Section508.gov, Define Accessibility Criteriasection508.gov/buy/define-accessibility-criteria | Model contract language asks for an ACR for each ICT item that is developed, updated or configured for the agency, and when product substitutions are offered, based on the latest version of the VPAT. | Updates and substitutions during a contract can each need their own report. |
| Section508.gov, Buy Accessible ICTsection508.gov/buy | ICT must remain accessible throughout the contract, so as products are updated or modified, agencies should re-test conformance of each new version. | A buyer may test your new version against the terms you agreed to. |
| ITI, VPAT 2.5Rev templateitic.org/policy/accessibility/vpat | If a report is revised, change the report date and explain the revision in the Notes section, or create a new report and say in the notes that it supersedes the earlier one. The template reports EN 301 549 V3.1.1 and V3.2.1. | Revisions are expected. Say what changed, on the page. |
| W3C, WCAG overvieww3.org/WAI/standards-guidelines/wcag | W3C encourages using the latest version of WCAG, and content that conforms to WCAG 2.2 also conforms to 2.1 and 2.0. | A 2.2 report answers a 2.1 or 2.0 requirement. A 2.1 report doesn’t answer a 2.2 one. |
| Access Board, Revised 508 Standardsaccess-board.gov/ict | Web content and software must conform to WCAG 2.0 Level A and AA. | A new WCAG version doesn’t, by itself, change what Section 508 requires. |
| ETSI, EN 301 549 V4.1.1etsi.org/deliver/etsi_en/301500_301599/301549/04.01.01_60 | Published September 2026. Clauses 9, 10 and 11 are updated to align with WCAG 2.2. Conflicting national standards are to be withdrawn by May 31, 2028. | European buyers will start asking for it. The VPAT template hasn’t caught up yet. |
Each row was read from the page or document it links to on . The ITI row comes from the INT edition Word file on that page. Section508.gov dates its own reviews at the foot of each page, and the four above were last reviewed between September 2025 and August 2026.
What to Do Between Full Re-Tests
Not every release needs a new report from scratch. A small release can get a revised report, as long as the revision is honest about what was and wasn’t tested again. ITI’s template gives you the fields for it.
- Keep the version field current. Name the version the report covers. If a release changed nothing a user sees, you can say in the notes that the report also applies to it, but only if that’s true.
- Change the report date and explain why. ITI’s rule is to change the date on a revised report and explain the revision in the notes, or to issue a new report that says it supersedes the old one.
- Keep a short change log in the notes. ITI lists revisions to the document and the product version it covers among the things the notes are for. One line per revision is enough: the date, the version, and what was tested again.
- Date the remarks you change. A remark such as “Fixed in version 4.3 and re-tested October 2026” tells a reviewer which answers are new and which are carried over.
- Re-test before you change an answer. Moving a row from Partially Supports to Supports because a ticket was closed is a claim with nothing behind it. Test the screens that changed against the criteria they touch, and say in the evaluation methods what the revision covered.
- Know when a revision isn’t enough. A redesign, a new design system or a new major version usually touches too many rows to patch. That’s the point to test again in full.
Every field named above is covered in how to fill out a VPAT, and Harbor’s sample VPAT/ACR shows a finished report with its version, date and notes filled in.
What WCAG 2.2 Means for an Existing Report
WCAG 2.2 became a W3C Recommendation on October 5, 2023. It adds nine success criteria, six of them at Level A or AA, and removes 4.1.1 Parsing. The W3C says content that conforms to 2.2 also conforms to 2.1 and 2.0, and encourages using the latest version.
A report tested against WCAG 2.1 doesn’t become wrong when 2.2 arrives. It’s still an accurate answer to the question it was written for. It just isn’t a 2.2 answer. If a buyer asks for 2.2, or your contracts start naming it, you’ll need to test the six new criteria (Focus Not Obscured, Dragging Movements, Target Size, Consistent Help, Redundant Entry and Accessible Authentication), add their rows, and mark 4.1.1 as not applying under 2.2, which is what ITI’s template says to do. If the product changed since the last test, test the rest again too. Section 508 still incorporates WCAG 2.0, so a 2.2 update isn’t required for that reason alone. The full list of changes is in WCAG 2.1 vs 2.2.
What EN 301 549 V4.1.1 Means for an Existing Report
ETSI published EN 301 549 V4.1.1 in September 2026. Its web, non-web document and software clauses are updated to align with WCAG 2.2, and it adds a way to evaluate products against the European Accessibility Act’s requirements. The standard’s own dates give national standards bodies until May 31, 2027 to publish it and until May 31, 2028 to withdraw conflicting national standards.
The VPAT hasn’t caught up. ITI’s current template, VPAT 2.5Rev, reports against EN 301 549 V3.1.1 and V3.2.1, and its VPAT page announced no new version when we checked on . So an EU or INT edition report written today is a V3.2.1 answer, and that’s what the template supports. If a buyer asks for V4.1.1 by name, say in the notes which version the report covers, point to the WCAG 2.2 tables if you have them, and ask whether that works for them. When ITI releases a template that covers V4.1.1, that’s a good time to plan the next revision. Which edition carries which standard is in which VPAT edition do you need.
Planning for It
The simplest habit is to tie the report to your release calendar. When a release changes what users see, put a re-test of the changed screens on the release checklist, and plan a full re-test for redesigns and major versions. If a renewal or an RFP is coming, check its wording for a report age, a WCAG version or a template version before you send what you have. If you’re weighing doing the next one in house against paying for it, how much a VPAT costs covers what providers publish and what the fee counts.
How Harbor Does It
Harbor is led by Andrew Szigety, DHS Trusted Tester TT‑2606‑09221. Every unique template is tested by hand against all 55 WCAG 2.2 Level A and AA criteria, and the ACR is tested and signed by a DHS Trusted Tester who is named in it, along with the methods used, the product version and the report date. Every report comes in the INT edition, so one document answers a WCAG, a Section 508 or an EN 301 549 request.
Follow-up reviews are part of every engagement. As your team lands fixes, the changed screens are tested again and the ACR is re-issued after each review, with the revision explained in its notes. When a later release or a redesign needs a new report, it’s scoped the same way as the first, on a free 15-minute call. Harbor doesn’t publish a fee. It follows your unique template count and is fixed in writing before you commit. The VPAT/ACR service page covers what an engagement includes.
Harbor provides technical audits and conformance documentation, not legal advice. What a particular buyer accepts is set by that buyer and its solicitation. VPAT® is a registered service mark of the Information Technology Industry Council (ITI).
- Read the Sample VPAT/ACR
- How to Fill Out a VPAT
- WCAG 2.1 vs 2.2
- Which VPAT Edition You Need
- Book the 15-Minute Call
Common Questions
- Does a VPAT expire?
- No. Neither ITI, which publishes the VPAT, nor section508.gov sets an expiry date for a completed VPAT, which is called an Accessibility Conformance Report (ACR). The report describes one product version on one date. Section508.gov says that every time a product is changed or updated, such as a version change or a bug fix, an updated ACR may be required to address any changes in its accessibility. Checked on October 14, 2026.
- How often should a VPAT be updated?
- Whenever the product changes in a way that could affect accessibility: a release that changes the interface, a redesign, or a new module or flow. Also update it when a buyer asks for a newer report, a newer WCAG version or the current template. Neither ITI nor section508.gov sets a calendar interval for updating an ACR, though some buyer questionnaires do.
- How old can an ACR be for an RFP?
- The solicitation decides, and there is no single federal number. Section508.gov’s model contract language asks for an ACR for each ICT item, including updated ones, based on the latest VPAT version, and tells agencies to test commercially available release versions. Some questionnaires set a window: the HECVAT that colleges send vendors asks whether the ACR was created or updated for the version under consideration within the past 12 months.
- Do I need a new VPAT for WCAG 2.2?
- Only if a buyer asks for 2.2 or you want to claim it. A report tested against WCAG 2.1 is still accurate for what it claims, and the Revised Section 508 Standards still incorporate WCAG 2.0. To report on 2.2, test the six new Level A and AA criteria, add their rows, and mark 4.1.1 Parsing as not applying under 2.2. The W3C encourages using the latest version.
- Does EN 301 549 V4.1.1 make my ACR out of date?
- Not by itself. ETSI published EN 301 549 V4.1.1 in September 2026, with its web, document and software clauses aligned to WCAG 2.2. ITI’s VPAT 2.5Rev template still reports against V3.1.1 and V3.2.1, checked on October 14, 2026. ETSI’s own dates give national standards bodies until May 31, 2028 to withdraw conflicting standards. If a buyer asks for V4.1.1, say in the notes which version your report covers and ask whether that works.
- How do I update a VPAT without starting over?
- ITI’s template says that if a report is revised, change the report date and explain the revision in the Notes section, or create a new report and say in the notes that it supersedes the earlier one. Update the product version, re-test the screens that changed, and change a conformance level only after testing shows it changed.